4.If the AC exceeds the EV, the cost estimate at completion will
Answer:
a. decrease
b. increase
c. exceed the schedule estimate at completion
d. depend on the PV
5.The pricing of a project can be extremely complex in the development of valid cost estimates and price quotes from vendors. The tool that facilitates the pricing of a project by a structured decomposition of the total into individual elements of labor, material and equipment is the
Answer:
a. budget
b. work breakdown structure
c. configuration management plan
d. project management plan
6.A project manager performs Earned Value Analysis and finds the following results:
EV: 250,000; PV: 200,000; AC:275,000
BAC is 500,000
What is right?
Answer:
a. BTC = 400,000
b. ETC = 75,000
c. EAC = 550,000
d. EAC = 400,000
7.During a software project Earned Value Analysis is performed and gives the following results:
EV: 523,000; PV: 623,000; AC:643,000
Answer:
a. CV: - 100,000; SV: -120,000
b. CV